July 10th - View of old bathroom before demolition begins
July 11th - Bathroom gutted, old window still in place
July 12th - New smaller window & framing in place
July 17th - New drain, plumbing & floor lining in place
July 19th - Shower wall is sheetrocked & waterproofed
July 22nd - Wet area cement board in place in shower
July 23rd - Shower wall tile underway
July 24th - Shower wall tile almost finished
July 25th - Shower floor tile in place at lunchtime
July 26th - Floor tile and shower lip tile in place
July 29th - Closet, vanities & shower grout installed
August 8th - Sink & shower faucets installed (Counter 8/6)
August 15th - Mirror frame, racks, & cabinet handles added
August 28th - Glass in place, sealant dried, Done!