Bathroom Remodel Day 3 - July 16, 2013


D0 D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 DW C


Paper and plastic in place to protect the floor and carpet

Sheetrock tracks now and concrete dust later in the day

Old humidity vent to be removed & sheetrock patched over

New humidity vent in center of room & higher up

Redundant GFCI safety outlet removed & outlet rotated

Below counter outlet raised above & 3rd outlet added

High boards added for the shower pan water proofing

Old bathroom window hole being bricked over

Wall is done, now to finish the shelf under the new window

Acid wash to age it some tomorrow and then complete