Door Way View Progression - July 2013


D0 D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 DW C


July 10th - Day before demolition begins

July 12th - Demolition done & framing begun

July 17th - New shower plumbing, flooring begun

July 19th - Sheetrock and waterproof sheeting in place

July 22nd - Concrete board in place

July 23rd - Shower tile underway, composite floor in place

July 24th - Shower tile continues, nook tile in place

July 25th - Floor & shower floor tile in place

July 26th - Closet wall angled for 90° glass connection

July 29th - Closet, vanities & shower grout installed

August 6th - Counter top installed

August 8th - Shower, sink faucet & toilet fixtures installed

August 15th - Door knobs, racks and mirror frame added

August 15th - Mirror & angled bracket delay completion

August 28th - Door installed and sealant dry, Done!