New Porch Day 11 - February 6th, 2023
OLD
D1
D2
D3
D4
D5
D6
D7
D8
D9
D10
D11
D12
D13
D14
D15
D16
Day 11 has the bricks being returned to the wall completing the porch
The old bricks have been cleaned of mortar and a few extra brought along
Our mason clears the mortar off the standing brick wall
The bricks are ready for new mortar and the debris will cleared shortly
Left side corner ready to receive new bricks and mortar
Left side corner complete with mortar now drying
Right side corner ready to receive new bricks and mortar
Now need gutters/drainage and new concrete treatment for completion